The District Department of Transportation (DDOT) will be temporarily restricting the parking lane on the west side of 15th Street NW, from K Street to Swann Street, to repave the 15th Street Cycletrack. This will impact parking in the area of the A&T Alumni House located at 1810 15th Street Northwest. The DC Chapter encourages all members to use Metrorail/Metrobus/DC Circulator, or park at the free and paid parking lots nearby.
Directions to the A&T Alumni House & Parking Information: news.wdc-ncatalumni.org/about-us/directions-to-the-alumni-house/
As you travel to chapter meeting on Friday September 6, please be cognizant of these changes.
Directions to the A&T Alumni House & Parking Information: news.wdc-ncatalumni.org/about-us/directions-to-the-alumni-house/
(Washington DC) The District Department of Transportation (DDOT) will be temporarily restricting the parking lane on the west side of 15th Street NW, from K Street to Swann Street, to repave the 15th Street Cycletrack. While the cycletrack is being repaved, bicyclists are advised to use alternate routes, such as 14th Street and 16th Street NW.
The temporary parking restrictions are scheduled to begin on or about Friday, September 6, 2013 and continue through Friday, October 11, 2013, weather permitting.
The project is scheduled to be completed in several phases. The first phase—which will involve repairs to curbs, gutters, and pedestrian ramps along the corridor—will take approximately two weeks to complete and affect two-block segments at a time. During this phase, temporary No Parking signs will be posted in advance along the affected segments so that residents have adequate notice to move their cars to another location.
The next phases of the project—which involve resurfacing the 15th Street Cycletrack, installation of pavement markings—will be done in two, larger segments. During these phases, DDOT will also provide advanced notice via temporary No Parking signs.
For more information about this work, please contact Project Engineer Delante Toyer (202)671-4661 or atDelante.toyer@dc.gov.
The temporary parking restrictions are scheduled to begin on or about Friday, September 6, 2013 and continue through Friday, October 11, 2013, weather permitting.
The project is scheduled to be completed in several phases. The first phase—which will involve repairs to curbs, gutters, and pedestrian ramps along the corridor—will take approximately two weeks to complete and affect two-block segments at a time. During this phase, temporary No Parking signs will be posted in advance along the affected segments so that residents have adequate notice to move their cars to another location.
The next phases of the project—which involve resurfacing the 15th Street Cycletrack, installation of pavement markings—will be done in two, larger segments. During these phases, DDOT will also provide advanced notice via temporary No Parking signs.
For more information about this work, please contact Project Engineer Delante Toyer (202)671-4661 or atDelante.toyer@dc.gov.